Connecting solar to the grid in Chester: SP Energy Networks, G98 and G99

Every solar system in Chester ends up connected to the same local network, and there is a rule about how. Most homeowners never deal with it directly, but it decides whether an installation can go ahead straight away or has to wait for approval. This page explains the two routes and who does what.

Last reviewed · Published by SEO-DONS LTD · How we check facts

Three companies, three different jobs

People often assume the company that sends their electricity bill is the one that decides about solar. It is not. Three parties are involved in connecting panels to the grid in Chester, and it helps to know which is which before you read a quote.

Who does what when solar is connected in Chester. Network details from SP Energy Networks and Cheshire West and Chester Council, read 3 November 2026.
WhoWhat they areWhat they do for your solar
SP Energy NetworksThe network operator for the SP Manweb licence area, which covers Merseyside, North Wales and parts of Cheshire, Chester among themReceives the G98 notification, or decides the G99 application and any export limit
Your electricity supplierThe company you buy electricity from and pay bills toCan pay you for exported power under the Smart Export Guarantee
Your MCS installerThe firm that designs and fits the systemDesigns to a route, notifies or applies to the network operator, and issues the MCS certificate
YouThe householderChoose the installer and the export tariff, and keep the paperwork

SP Energy Networks sets out its rules on its connecting to the grid page, and Cheshire West and Chester Council’s support schemes page also names it as the local electricity network operator. You do not choose your network operator; it comes with the address. You do choose your supplier, and you can change it.

G98: connect first, then notify

G98 is an Engineering Recommendation, one of the technical standards the electricity industry uses for connecting small generators to the local network. It covers generation of up to 16 amps per phase. On a single-phase supply, the kind most homes have, that works out at 3.68 kW: 16 amps at the standard 230 volts.

“Single-phase” and “three-phase” describe how electricity reaches the building. A single-phase supply has one live conductor coming in to the meter, and it is what most houses and flats have. A three-phase supply has three, and is found in some larger homes and in buildings with heavy loads. The installer checks which one you have, and the answer feeds straight into which route applies.

Under G98 the installer connects the system and then notifies SP Energy Networks within 28 days. Nothing has to be approved in advance, so if a design fits under the limit there is no wait for the network operator at all.

What counts towards the limit is output, measured at the inverter. The inverter is the unit that converts direct current from the panels, or from a battery, into the alternating current the house uses. When you compare quotes, ask what each inverter is rated at and whether the design is meant to stay within G98.

G99: apply before anything is fitted

Anything above the G98 limit goes through G99. That includes larger arrays, homes on a three-phase supply, and solar plus a battery whose combined inverter output is over the limit. The installer applies to SP Energy Networks before installation. Approval can take weeks, and the network operator may set an export limit as a condition.

An export limit is a cap on how much power the system may send to the grid at any one time. It restricts what can flow out, not what the panels make for use in the house. If one is set, the design has to keep to it, so ask the installer how theirs would.

Treat a G99 decision as a step in the timetable, in the same way as planning consent on a listed building. Equipment that needs approval should not be fitted before the approval is in writing.

Which route a design takes, from SP Energy Networks’ connection rules read 3 November 2026. The installer confirms the route for each design.
SituationRoute
Inverter output up to 3.68 kW on a single-phase supplyG98: connect, then notify within 28 days
Inverter output above 3.68 kW on a single-phase supplyG99: apply and wait for approval before installation
Solar plus a battery with combined inverter output above 3.68 kWG99: apply and wait for approval before installation
A battery or more panels added to an existing systemThe combined output decides; ask before ordering
A three-phase supplyAsk the installer which route the design takes

What the installer should do, in order

A competent MCS installer handles the network side as part of the job. You do not need to contact SP Energy Networks yourself, but you should know the sequence so you can tell whether it has been followed.

  1. Check the supply. Whether it is single-phase or three-phase, and whether there is any existing generation, such as older panels, that counts towards the total.
  2. Design to a route. State the inverter rating and the combined output with any battery, and say in the quote whether that means G98 or G99.
  3. For G99, apply first. Submit the application to SP Energy Networks and wait for approval, including any export limit, before fitting.
  4. Install and commission the system, which means setting it up and testing it before handover.
  5. For G98, notify SP Energy Networks within 28 days of connection.
  6. Hand over the paperwork. The MCS certificate, the commissioning record, and a copy of the G98 notification or the G99 approval. Keep them with the house documents, because a buyer may ask for them when you sell.

The wider checks on an installer, from the MCS directory to the consumer code, are in our guide to choosing a solar installer in Chester.

Planning a timetable around G99

A G99 wait only matters if there is a date you care about, and at the moment there is one: VAT on installed home solar and batteries is 0% until the end of March 2027, then 5% from 1 April 2027 (HMRC VAT Notice 708/6). If a design needs G99, ask the installer when the application will go in and plan from there.

Grid connection and planning are separate processes, and neither stands in for the other. A listed home needs planning permission and Listed Building Consent before work starts, as our listed buildings guide explains, and that is in addition to any G99 approval. A shared array on a block of flats may need G99 as well as the freeholder’s consent; see our flats guide.

Being paid for what you export

Connection and payment are separate too. SP Energy Networks connects the system; it does not pay for exported power. Payment comes from an electricity supplier under the Smart Export Guarantee, which Ofgem administers. Licensed suppliers must offer an export tariff above zero for systems up to 50 kW. To qualify, the installation must be MCS certified and you need a smart meter that can record exports. Tariffs vary from supplier to supplier and there is no single SEG rate, so compare them before you sign up.

Most exporting happens between spring and early autumn, when the panels make more than the house uses. To see what a Chester roof is likely to produce through the year, use our roof output estimator.

Chester situations that come up

  • Larger detached houses. Handbridge Park has the highest share of detached homes of Chester’s seven wards, 37.5% of households according to Census 2021. Bigger roofs make bigger arrays possible, and a bigger array is more likely to go past the G98 limit, so ask early which route a design takes.
  • Adding a battery later. The new equipment counts alongside the old, so a battery added to panels already on the roof can turn a G98 system into a G99 one. Our battery guide covers this.
  • Buying through the council’s group-buy. The same G98 and G99 rules apply to a Switch Together Solar installation as to any other; the network does not treat it differently. See our Switch Together guide.
  • A listed home in the centre. The planning consents come first, and the grid step still applies to whatever is approved.

Questions to put to an installer about the connection

  • What is the inverter rating, and what is the combined output with any battery?
  • Does this design go through G98 or G99, and who makes the notification or application?
  • If it is G99, when will the application go in, and will you wait for approval before fitting anything?
  • If an export limit is set, how will the system keep to it?
  • Will I get copies of the MCS certificate, the commissioning record and the network paperwork?

Grid connection questions from Chester homeowners

Do I have to tell SP Energy Networks about solar panels in Chester?

Yes, but your installer does it for you. For a system up to 16 A per phase, which is 3.68 kW on a single-phase supply, the installer connects it and then notifies SP Energy Networks within 28 days. For a bigger system, or panels plus a battery that together exceed the limit, the installer applies first and waits for approval before fitting anything.

How long does a G99 application take?

Approval from SP Energy Networks can take weeks, so build it into the timetable rather than expecting a quick answer. The installer submits the application before installation. Ask when it will go in, what the design’s combined inverter output is and whether an export limit has been set, and do not let work start until the approval is in writing.

What is an export limit?

A cap, set by the network operator, on how much power your system may send to the grid at any one moment. It can come with a G99 approval. It restricts what flows out to the grid, not what the panels produce for use in your home. Ask the installer how the design would keep to any limit that is set.

Is SP Energy Networks my electricity supplier?

No. SP Energy Networks runs the cables and substations that carry electricity around the area and handles connections to them. Your supplier is the company that bills you, a separate business that you choose and can change. Payments for exported solar power under the Smart Export Guarantee come from a supplier, not from the network operator.

Do I need a smart meter to be paid for exported solar power?

To be paid under the Smart Export Guarantee, yes. You need a smart meter that can record exports, and the installation must be MCS certified. Licensed suppliers must offer an export tariff above zero, but rates and terms vary from one supplier to another, so compare several before you choose one.

Sources for this page

Read at source on 3 November 2026. If something has changed, tell us through the form and we will correct it.

  1. Connecting to the grid · SP Energy Networks
  2. Support schemes (home energy) · Cheshire West and Chester Council
  3. VAT on energy-saving materials and heating equipment (VAT Notice 708/6) · HM Revenue & Customs
  4. Smart Export Guarantee (SEG) · Ofgem
  5. Census 2021 tables TS044, TS054 and TS046 by 2022 ward · Office for National Statistics, via Nomis

Want a second pair of eyes on your Chester home?

Say what sort of home you have, roughly where in Chester it is, and what you are weighing up: panels, a battery, a planning question or a quote you have been given. The message reaches SEO-DONS LTD, the company behind this guide, and we answer by email.

What happens next

  1. Your message lands with SEO-DONS LTD, which writes and runs this Chester guide.
  2. We read what you have told us about the house and answer by email.
  3. Sending it does not sign you up to anything, and nobody will knock on your door.
Tell us more about the house (optional)

This guide is published by SEO-DONS LTD. We are not an installer, a council service or a scheme, and we answer enquiries by email. See our privacy notice.